This 10 MW solar power plant is a grid-feed-in solar power plant operating under the renewable energy support scheme of Iran.

The project was developed in partnership with an Iran engineering company. The project is solely financed by Nvision Green Energy.

Land rights were applied for in August of 2017 and all necessary permits, licenses and the power purchase agreement were obtained by March 2018. Construction was completed within 10 days in June 2018. The plant is operational since July 2nd 2018.

 

Capacity 9,360 kW
Modules 28,800 x 325 Wp p-Sci
Inverters 160 x SMA STP 50000
Grid connection 10,000 kVA 0.4/20 kV
Type Grid-feed-in
Monitoring Nvision Green Energy sDashboard
PPA signing Mar 2018
Procurement Mar/Apr 2018
Freight & import Apr/May 2018
Construction Apr/May 2018
Solar yield 1,765 kWh/kW/year